After the School holidays, there’s always exciting progress with which to update the Trinity community. Without students and staff on campus, more progress can be made without disruption – it’s always good news for the Renewal Project.

In April the following works were completed: 

  • In-ground foundations were 90% completed and shoring walls to the East were 100% completed. 
  • Stormwater and sewer service connections for the showers and toilet blocks commenced. 
  • The footings for the static concrete pump were installed – this will service all the concrete pours from ground level through to the roof level, so this is an integral piece of work. 
  • Lift shaft foundations and wall works commenced. 
  • The internal strip out of the Quad building has now been completed and further progress is pending structural advice from engineers regarding undocumented structural elements. 

Ahead in May: 

  • The completion of in-ground stormwater and sewer pipework connections. 
  • Commencement of reinforcement and forming of the ground floor slab. 
  • The first concrete pour is expected to take place in late May.

 

Questions or concerns? Contact Scott Swann, Director of Major Projects, Trinity Grammar School via the contact form on our website found here.